Appendix 5
22 Nov 2018
Yes
-  

 

 

Site Induction Arrangements

No

​​

 

STFC Site Specific Induction:

STFC induction will be required for all persons coming onto site including Principal Designer, Designers, Principal Contractor, and Contractors associated with a project. The STFC induction is to be completed and passed before being allowed on the STFC site.

CDM Site Specific Induction (e.g. by the Principal Contractor):​

This needs to be specific to the project with information about particular risks associated with the CDM site and arrangements that have been made for their control.

The site induction should include a site specific explanation of the following:

  1. STFC commitment to health and safety
  2. An outline of the project
  3. Any site specific health and safety risks
  4. Control measures on the site, including:
    • site rules
    • any permit to work systems
    • traffic routes
    • security arrangements
    • hearing protection zones
    • arrangements for personal protective equipment
    • housekeeping
    • materials storage
    • welfare facilities and
    • emergency procedures
  5. Arrangements for first aid
  6. Arrangements for reporting accidents and other incidents
  7. Any planned training including ‘toolbox’ talks
  8. Arrangements for consulting with the workers
  9. Information about the individual’s responsibilities for health and safety.
  10. ​​

Contact: Baker, Gareth (STFC,DL,COO)